Summary notes of the LCU meeting on 22/01/2013

Present: FB, HB, JJ, RDM, LD, OD, MG, PH, BH, EM, MS, GV, RV

Report from meetings

WP8 activities -> FB (slides)

Frederic, who recently joined our group, reported about the activities in the working package 8 for the HL-LHC on machine detector interface and on his  contributions to this work.
For the HL-LHC it will be important to include the experiments requests in a coherent planning and to avoid last minute changes. One key point and starting point for his work is to study the consequences of opening up the TAS radius as required for the HL-LHC to a radius which will be much larger than the reduced central detector beam-pipes.
He started to collect the available aperture information and estimates for the HL-LHC as input for tracking studies. These studies will be done in close collaboration with other HL-LHC working packages like collimation and energy deposition.
Laurent warned that we should be aware that MAD-X is currently not always precise in the prediction of the intersection of tracks with apertures. 


Ion commissioning status -> RV (slides)

Reine presented an overview of the ion commissioning with input from Michaela and John.

The commissioning started on Friday, 11 January, when first Pb ions were injected in the LHC this year. 
A lot of detailed work has been done since, including the commissioning of the squeeze to the p-Pb target values (0.8, 0.8, 0.8, 2.0 m for IPs 1,2,5,8) and collimation and machine protection. First stable beams were reached on the 20/1. Over the weekend  and on Monday, the number of bunches was increased and just reached the nominal value of 338 bunches. Beta-beating was measured and corrected including the off-momentum knob test and correction. Close parasitic beam-beam encounters around ALICE seem not to cause problems.
The p-Pb run started well. 


AOB

None