Summary notes of the LCU meeting on 01/07/2008
Present: IA, HB, RC, SF, MG, WH, JJ, PL, AM, JN, TP, TR, FR, RT, TW, SW
Report from meetings
Status of optics database for LHC commissioning (V6.503 optics) -> TR
The commissioning group would like to use as much as possible 
up-to-date files for the actual machine and decided to use optics V6.503, even 
if some details are still evolving. The sequence is considered to be debugged 
and S. Chemly should have launched a request of feedback before formally approve 
it. 
In parallel, there has been work at the level of the layout database to provide 
the information concerning the aperture of vacuum elements. The information will 
be stored in a file with the marked definition, mechanical tolerances, and the 
installation of the markers. There are still discussions on-going to specify 
generic tolerances to be included in this file.
The use of this information highlighted a number of aperture bottlenecks, which 
were not known before. In particular, it was found that the aperture at the 
flange between Q1 and Q2, is below n1=7 at injection. The following approach is 
followed:
IR1/5: the crossing angle is 190 murad. By reducing it to 170 murad (which is 
the nominal value for IR2/8 and hence is considered acceptable) the aperture 
bottlenecks disappear. 
IR2/8: three options are possible, namely: reduction of the parallel separation 
(it is considered acceptable); reducing the budget for closed orbit; increase 
the value of beta*. The latter should be carefully evaluated in terms of impact 
on the phase advance constraints between injection/protection devices.
These activities are in progress (contributions by Thys, Werner and Stephane)...
AOB
None