Presents: WH, MG, BJ, RdM, AM, YP, FR, TR, FS, RT, TW, FZ.
- Follow up of actions
- VELO detector and spectrometer strength for
LHCb -> YP (pdf
file)
- YP first mentions that a bug was discovered on the MADX
aperture module regarding the slicing of kickers. An easy by-pass of
the problem is achieved by introducing slice lengths which are longer
than the kickers. JBJ will look into the problem in due time.
- YP presents a complementary study regarding the aperture on
IR8 at 450 GeV when the spectrometer has its full strength. A request
was made by the experiment to check if there is any possibility to have
also the VELO detector closed at 5mm during the early run next year.
- Using analytical estimates and simulations with MADX,
it is shown that, provided that the instrument can be centered around
the closed orbit, the VELO cannot be closed to less than 5.6 mm without
internal crossing angle or 7.2 mm for the extreme internal crossing
angle. However, a magnet-like 2.2 mm mechanical tolerance was used in
the evaluation of the n1. With tighter mechanical tolerance for the VELO
assembly, 2 extra mm can be
gained for the closure of the VELO.
- MG suggests that a table with the values for the closure of
the VELO at top energy is
included. The results will be refined and presented at the next LTC.
- Squeeze study for LHCCWG -> MG (pdf
file)
- Proposed topic by Roger Bailey to be covered in LHCCWG of
29th of November
- Shared in three presentations (LOC, collimators and
operation) with the following questions
-
mechanics: is it any different
from the ramp?
- intermediate optics: how many and
which ones?
- influence of optics changes on
crossing angle (when we have one)?
- energy?
- collimators: when do we move them?
- do 1 and 5 together? what about 2 and
8?
- machine protection
- Proposal for LOC work
- IR2 (JJ) and IR8 (YP), IR1-5 (MG and SF)
- Report from meetings
- MEB -> MG
- The big issue is the performance of Q5R5 magnet
(SSS650). After the thermal cycle the magnet did not reach nominal
performance. A decision was taken to stop the test, based on a
statement by Ranko that operational currents were lower than
nominal, without any communication from ABP-LOC. Actually, the current
for 17 m β* presents only 10A safety margin and for TOTEM optics there
is none. Nevertheless, the
magnet was stripped and
presented at MEB.
At first it was considered as a viable option to repeat the test in the
tunnel. After discussions, a possibility appeared to prepare a spare
magnet to replace this one
with minor hardware modifications. The cold test of this
magnet will be redone and in case of failure, the transformation of the spare magnet
for Q8 into a spare magnet for Q5R5 will
be launched.
- A complete reshuffling of the pre-allocation list of the SSS in Sector 2-3 was performed
in order to cope with installation from the right side of IP3. 19
already approved magnets had to change slots.
- Beta correction at the KEKB rings -> Akio
Morita (pdf
file)
- Akio Morita presents the on-momentum beta correction used in KEKB in routine operation and the first attempts to do an off-momentum
beta correction.
- Available monitors include the tune monitor and the TBT BPM
system. The available knobs are the dipole and quadrupole currents.
- The basic idea is to fit the measured response of a dipole
kick to an analytic formula using the beta function and phase advance.
The fit is done either through least squares minimization of
polynomial function, or by reducing dimension of the problem with
some assumptions, or by brute force fitting, this last being very slow.
An improved fitting scheme
based on Newton-Raphson method exists.
- The beta correction is based on the fit between measurement
and
model using as knobs the quadrupole fudge factor and horizontal
cosine-like bump around the sextupoles. An extra weight is applied for
the tunes and the fudge factor of the real machine is iteratively
updated.
- One
correction is applied every two weeks, implemented on SAD and fully
automatic.
Each iteration takes 7 minutes and the usual correction time takes 30-60
minutes per ring. Typical performance is a final beta beating of 10% and tune
correction to better than 3 x 10-4.
- Off-momentum beta function correction is performed by
minimizing the difference between measured and model optics using the
54 sextupole families around the ring. Disturbing effects can come from
coupling close to the
sextupoles. Examples are shown, but some disagreement is found between
the measurement and model
- RT asks what is the initial beta beating. Akio
Morita answers that it is 20%. The BPM resolution is 1μm.
- MG asks what happens with dispersion? Akio Morita answers that the
dispersion remains uncorrected.
- Tunability of IR4 for the new optics scheme ->
TR
- New aperture was introduced and test with latest optics of
IR4 was made. No significant change with respect to what was found by André Verdier
is observed. There are some problems with the automatic matching
process. Riccardo de Maria is informed.
- Aperture issues for vacuum chambers between D1 and
D2 in IR2 and 8 -> JBJ (pdf
file)
- JBJ explains that these are preliminary results taking into
account all the changes in the injection kicker area.
- Initially, there was no dipole for the beam-beam
crossing
scheme. Since then, three orbit correctors and an extra BPM were
added
- For an injected beam with no secondary halo and kicker
misfire there are only 5σ at the entrance of the kicker. Then the BPMWB goes down to
3σ and the ZDC Y-chamber around 5σ
- On injection elements a 2mm orbit tolerance is being
enforced. Again ZDC and y-chamber is problematic especially whenever 4mm
orbit tolerance is used for both beams in conjunction with a non-elliptical chamber.
The case of an
elliptical chamber it is a bit better.
- Collective effects have to be discussed as well.
- For 450GeV run no crossing scheme is included but still the
bottleneck is found in the Y-vacuum chamber area.
- YP asks if there will be more aperture bottlenecks between
Q1 (L/R) especially for the high spectrometer values. JBJ replies
that probably the TCT will do its job, but still some particles may
flow around this area.
- MG suggests that this should be submitted to LHC Machine Protection Working
Group.
- TR suggests to check the impact with the new topics.
- AOB
Color code:
Black: proposed agenda
Red: outcome
of discussion at the meeting
Last update on 22-11-2006 13:00:00
MG
& YP