Summary notes of the LCU meeting on 08/09/2009
Present: RA, OB, HB, RDM, MG, WH, BH, JJ, EL, YL, JN, TR, AR, YS, RT, GV, SW, DW, FZ
Report from meetings
- SLM and general information -> MG
HW commissioning needs volunteers for patrols who are asked to contact
MG.
There has been a follow up on apertures around the interaction regions with a
presentation by MG of the current apertures in the meeting by
R. Veness for beam pipe upgrades. The original specification of 15 mm
mechanical tolerance allowed for initial large vertical movements of the experimental caverns. This is now settled and
would allow decreasing the tolerance safely to 11 mm. With the 15 mm
mechanical tolerance there is an aperture bottleneck at the level of the CT2
section of the CMS experimental vacuum pipe (injection and collision).
RA comments that this is a serious issue and should be
fixed by increasing beta* at injection from the current nominal value of 11
m to the old value of 17 m. MG comments that Ray and the CMS technical co-ordinator
are informed of this situation and are expected to provide some feedback
concerning whether the assumed value is compatible with the mechanical
construction of the vacuum pipe (e.g., the CT2 section is not too far away
from the TAS where a mechanical tolerance of 1 mm is assumed: this situation
does not seem to be possible from a mechanical point of view). After the
meeting MG discussed with SF: the change
of beta* at injection will generate a negligible variation of beta at the
level of the CT2 section of the CMS vacuum pipe, hence excluding this
solution.
Concerning alignment measurements, the vacuum chambers in LLS1 and 5 were
re-aligned and they are all within
±3 mm. In case of LSS5 few vacuum chambers are
displaced by up to 9 mm due to a collision with the collimators aside. The consequences of this will be checked for collimation. TAS positions in ATLAS were measured.
On the right side, displacements up to 1.3 mm were observed. A re-alignment
was requested provided this is compatible with the hardware constraints on
transverse displacement of bellows. The longitudinal alignment is also not
nominal and should be reflected in the as-built database.
The staff reduction imposed to CERN some years ago was reached and CERN should now again be able to replace positions for staff leaving CERN. New job openings can be expected soon.
A post on FIDEL implementation and settings generation is assigned to BE-ABP-LCU.
the board is being organized.
- CWG -> RA (slides)
Collimation working group meetings have been restarted. RA reported from the last
meeting. Collimator settings and the commissioning procedures are being defined in detail in the CWG.
The organization of the Phase II collimation was also
presented.
- LBS -> HB
The LHC background study group had its 6th meeting on Aug. 26. Slides and minutes are on indico. The last meeting was mostly on simulation with a discussion on the update of beam parameters relevant for simulations of the 3.5 TeV run.
Brainstorming discussion of beam parameters for 3.5 TeV run -> WH (slides)
Based on discussions in Chamonix 2009 and with the recent decision
to have a run at intermediate energy of 3.5 TeV, a new set of beam parameters
was collected by Mike Lamont and discussed in the commissioning meetings.
RA reminded that he requires for collimation an aperture of at least 11.3 sigma for intermediate collimator settings, and asked to determine and list the minimum n1 for any of the options discussed.
This could be taken into account by specifying an interval of beta*
corresponding to n1min=11.3 sigma (intermediate collimators settings) and
n1min=7 sigma (nominal collimators settings). The two values will also
correspond to "easy" and "challenging" targets for the beam commissioning.
According to WH, there should be no problem down to 2 m beta*. Experimental magnets should be taken into account, as turned fully on, even at injection. The spectrometer polarity is important for the options with crossing angle and only one polarity for LHCb
will be used at 3.5 TeV.
There will be further follow up on parameters with a summary published as EDMS document
and the outcome reflected in the optics database. MG says he will
gather the relevant information concerning the longitudinal beam parameters as
it was done for the 2008 parameters at 5 TeV.
AOB
A new fellow Maria Del Carmen Alabau Pons working on the LHC beam commissioning
and online model under the supervision of FS started recently
her activity in our section.
A new student Cesar Octavio Dominguez (Spanish trainee programme) working on the LHC
performance model under the supervision of FZ also started
recently his activity in the section.
FZ informed us that he was asked to be the secretary of a new
CERN Machine Advisory Committee at CERN that will first meet on the 26 October.
Last update: 09-September-09
MG & HB
Back to LCU Minutes